Life Campus
Hamburg
Structural Complexity and Fire Safety
The project presents a high degree of geometric and technical complexity. The folded roof geometry over the agora requires precise detailing at ridges, valleys and edges. WIEHAG also engineered star-shaped steel connection nodes at key intersections of the roof system.
Additional challenges include fire-rated escape balconies in steel, calculated using temperature curves from external fire exposure – eliminating the need for fireproof coatings. Non-load-bearing exterior walls and timber panel façades are produced in prefabricated timber-frame construction, and EI60-rated wall assemblies meet stringent fire resistance requirements across the building zones.
- Client
- LIFE Hamburg Projektgesellschaft mbH & Co. KG
- Architect
- Behnisch Architekten, Stuttgart
- Total floor area
- 15,000 m²
- Partial general contractor for timber and concrete construction, including structural design from phase 2, workshop planning, production and installation
- WIEHAG Timber Construction
- Glulam volume
- 1,350 m³
- Construction start
- 2024
- Completion
- 2026 (planned)