Ingolstadt
A multi-storey
car park in timber
A milestone project for Ingolstadt: a multi-storey car park with an ecological design. The completed timber multi-storey car park sets a new benchmark for sustainable infrastructure.
WIEHAG was commissioned with the production, delivery and assembly of all timber components and façade elements.
Project profile
Client
City of Ingolstadt
Architect
PBB
Statics & Planning
PBB
Structural consulting & construction design, production & installation
WIEHAG Timber Construction
Volume GLT
1,500 m³
CLT volume incl. rondells
10,500 m²
Installation time mass timber
per storey 2.5 weeks
Completion
2025