AMAZON DELIVERY STATION DZM1
STOCKTON-ON-TEES (UK)
The Amazon Delivery Station DZM1 in Stockton-on-Tees presents new solutions for reducing CO2 emissions in logistics buildings across Europe. The 10,800 m² building combines innovative, low-carbon building materials with energy-efficient building technology. WIEHAG Timber Construction contributed its expertise in engineered timber construction through the manufacture and supply of the timber components for the load-bearing structure.
ZERO CARBON IN SIGHT
TIMBER AS PART OF THE SOLUTION
DZM1 is the first building in Amazon’s global network to pursue Zero Carbon Certification (v1.1) from the Living Future Institute. The choice of materials plays a central role in achieving these ambitious climate goals. Cross-laminated timber (CLT) and glulam replace CO2-intensive materials in the load-bearing structure while permanently storing carbon. According to Amazon, combining timber with newly developed, lower-carbon materials has reduced embodied carbon emissions by at least 20% compared with the original design.
This sustainable approach extends to the building’s ongoing operation. Heat pumps, photovoltaic systems and heat recovery all reduce energy demand to approximately half that of a comparable logistics building.
ENGINEERING, PRODUCTION, PROJECT MANAGEMENT
A POWERFUL COMBINATION
WIEHAG was responsible for the structural engineering, detailed design, production and logistics of the timber components, as well as the installation of the mezzanine floor. In total, we supplied 210 m³ of glulam and 130 m³ of cross-laminated timber (CLT) for the roof structure and mezzanine floor.
The nearly 20-metre-long glulam fish-belly beams were prefabricated at the WIEHAG Campus in Altheim (AT), delivered according to a precisely coordinated schedule and installed on site in close coordination with the steel construction partner.
This was followed by the installation of the glulam parallel beams and CLT panels for the mezzanine floor beneath the already completed hall roof. Close coordination between all trades and the seamless collaboration of engineering, production and project management ensured the successful delivery of the project.
DECARBONISING CONSTRUCTION
PROVEN AND NEW MATERIALS
Amazon adopted a proven hybrid timber construction method for the Delivery Station to reduce the building’s carbon footprint. Several newly developed, low-carbon building materials were also used together for the first time.
Cement-free paving stones, along with carbon-storing asphalt and concrete, are being tested under real-world conditions to assess their potential for future construction projects.
In this way, Amazon combines established construction methods with new technologies to decarbonise the construction industry.